• JBM
  • AA School
  • Buildings
  • Solar
  • About
Menu

John Berry Millard

29 South Street
Manasquan, NJ, 08736
9083975740
portfolio of projects

Your Custom Text Here

John Berry Millard

  • JBM
  • AA School
  • Buildings
  • Solar
  • About
DSCN1131.JPG

YOLO

Project Data

End-User: Yolo Medical Center

Installer: LB Electric

Location: 80, Main St, West Orange, NJ

Date of install:  July 2006 – Oct 2006

Size of system in kW: 55kW

Energy produced since installation

Special Challenges Met: 1) Project was delayed by Xantrax Inverter manufacturer, who shipped the wrong inverter and then a broken transformer.

Project Brief

Drill Construction has their offices in West Orange, NJ. LB Electric provided customer liaison and project management and were also the electrical contractor of record. Turtle Energy designed a Photovoltaic system to be installed on the building.

Turtle Energy undertook a detailed analysis of the site. This analysis was comprised of the following steps and implementation.

Shading Analysis

Optimal System Design and Concept Planning

Industrial Design of the Components of the System

Multi-Disciplinary Coordination with Architects, Structural Engineers, Electrical Engineers, and Construction Management.

The project commenced in July 2006 and the system was commissioned in October 2006. The size of the PV system for Drill Construction is 55kW.

The inverter for the project was originally specified to be a Satcon 50kW inverter. However the project schedule could not withstand the lead time for Satcon, therefore a Xantrax 45kW was ordered. Xantrax first sent an inverter with the wrong transformer in it, after which they sent another transformer that arrived in an undamaged box but the transformer inside was damaged. Finally they sent us the correct transformer. This all caused significant time delay and extra labor costs; however LB Electric and Turtle Energy were able to complete the project in time.

Fat Spaniel’s inverter direct internet-based monitoring system was implemented and Fat Spaniel data acquisition illustrations show snapshots of the actual energy generation by the PV system for Drill Construction. These measurements are in compliance with the predicted analysis done by TurtleEnergy and in some cases slightly exceed the target energy output range. Data monitoring results are available both on a real-time and historical basis. Measurements can be viewed on daily, weekly, monthly, yearly or lifetime intervals. The installed PV system has successfully helped reduce the on-grid energy usage.

For additional information on product specifications see the appropriate cut sheets listed below.

Satcon 50kw Inverter

Schott ASE 315w Module

Fat Spaniel (remote monitoring system)

Multi-Contact Connectors

ILSCO Direct Bury Grounding Lugs

YOLO

Project Data

End-User: Yolo Medical Center

Installer: LB Electric

Location: 80, Main St, West Orange, NJ

Date of install:  July 2006 – Oct 2006

Size of system in kW: 55kW

Energy produced since installation

Special Challenges Met: 1) Project was delayed by Xantrax Inverter manufacturer, who shipped the wrong inverter and then a broken transformer.

Project Brief

Drill Construction has their offices in West Orange, NJ. LB Electric provided customer liaison and project management and were also the electrical contractor of record. Turtle Energy designed a Photovoltaic system to be installed on the building.

Turtle Energy undertook a detailed analysis of the site. This analysis was comprised of the following steps and implementation.

Shading Analysis

Optimal System Design and Concept Planning

Industrial Design of the Components of the System

Multi-Disciplinary Coordination with Architects, Structural Engineers, Electrical Engineers, and Construction Management.

The project commenced in July 2006 and the system was commissioned in October 2006. The size of the PV system for Drill Construction is 55kW.

The inverter for the project was originally specified to be a Satcon 50kW inverter. However the project schedule could not withstand the lead time for Satcon, therefore a Xantrax 45kW was ordered. Xantrax first sent an inverter with the wrong transformer in it, after which they sent another transformer that arrived in an undamaged box but the transformer inside was damaged. Finally they sent us the correct transformer. This all caused significant time delay and extra labor costs; however LB Electric and Turtle Energy were able to complete the project in time.

Fat Spaniel’s inverter direct internet-based monitoring system was implemented and Fat Spaniel data acquisition illustrations show snapshots of the actual energy generation by the PV system for Drill Construction. These measurements are in compliance with the predicted analysis done by TurtleEnergy and in some cases slightly exceed the target energy output range. Data monitoring results are available both on a real-time and historical basis. Measurements can be viewed on daily, weekly, monthly, yearly or lifetime intervals. The installed PV system has successfully helped reduce the on-grid energy usage.

For additional information on product specifications see the appropriate cut sheets listed below.

Satcon 50kw Inverter

Schott ASE 315w Module

Fat Spaniel (remote monitoring system)

Multi-Contact Connectors

ILSCO Direct Bury Grounding Lugs

DSCN1134.JPG
DSCN1131.JPG
YOLO 02.jpg
DSCN1137.JPG
DSCN1139.JPG
DSCN1140.JPG
FH010024.jpg
FH010025.jpg
FH020003.jpg
FH020005.jpg
FH020006.jpg
FH020014.jpg
FH020015.jpg
FH020016.jpg
FH020017.jpg
FH020018.jpg
FH030003.jpg
FH030004.jpg
FH030005.jpg
FH030006.jpg
FH030007.jpg
FH030008.jpg
FH030020.jpg
FH030021.jpg
FH030022.jpg
FH030023.jpg
FH030024.jpg
FH030025.jpg

Powered by Squarespace